- the pressure block installation height must be consistent, usually in the level above the 150 ~ 200mm;;
- the pressure block welding requirements with three-sided spot welding, thermocouple insertion port do not spot welding, side spot welding to pay attention to the stop screws will not be welded to death.
- Pipe wall temperature should be installed symmetrically up and down.
- armoured thermocouple must be inserted into place, stop screws tightened in place.
- armoured thermocouple lead recommended to use a small slot box.
- armoured thermocouple fixed stainless steel wire must be used instead of;
- armoured thermocouple and furnace wall interface must be wrapped, and then threaded into the homemade protection tube leads;
- in order to prevent the boiler from settling, it is recommended to use the transition junction box, and then connected to the pre-positioner with a compensating wire.
- furnace wall and pre-positioning of the bridge or protection pipe should not be closed, to prevent high heat flow directly into the pre-positioning and damage to the components inside (Tianjin Electric Construction did not pay attention to, resulting in damage to the pre-positioning);;.
- the preamplifier installation location can not be too far, otherwise the length of the thermocouple is not enough;;.
- wiring should be correct, reliable.